Panel upgrade with SCE: the steps, in order, for a home on Southern California Edison

How a home panel upgrade works with Southern California Edison: sizing the service, SCE's project request, the inspection and getting the power back on.

Panel upgrade: new Square D main panel, meter socket and conduit
Panel upgrade: new Square D main panel, meter socket and conduit. Photo from one of our jobs.

A panel upgrade on a home served by Southern California Edison (SCE) runs through two offices: SCE, which owns the power up to your meter and has to agree to where the new panel and meter go, and your city or county building department, which issues the electrical permit and inspects the work. The usual order is: size the new service, open a request with SCE, get the permit, install, pass the inspection, and then SCE reconnects the service once the building department confirms the inspection.

This guide is for homes whose power bill comes from SCE: most of Orange and Ventura counties and most of Los Angeles County outside the City of Los Angeles. If your bill comes from LADWP, read our LADWP panel upgrade guide instead. Burbank, Glendale, Pasadena, Azusa, Vernon, part of Cerritos and Anaheim run their own utilities, and the southern end of Orange County is served by SDG&E; see who handles your permit and power. Utility lines can split a neighborhood, so check the name on your bill.

Step 1: Size the new service

Start with a load calculation: the home's current use plus anything new on the list, whether that's a car charger, a heat pump water heater, an electric range, a pool or spa, or an ADU. The result decides whether a larger service is needed at all, and how large.

It's worth asking the question honestly. SCE's own project request page points out that load management, energy-efficient equipment or design changes may support new loads without a larger service. Our articles on EV chargers on a 100-amp panel and heat pumps and induction ranges walk through ways to add load without a bigger service.

If the house does need a bigger service, SCE may have to change its own equipment to carry it, such as the conductors, the transformer or the meter. That is SCE's design work, and it's why the SCE request comes before the installation.

Step 2: Open a request with SCE

SCE's project request page lists "Panel upgrade (or meter spot) for an existing service connection" as its own request type, and says most requests can now be submitted online through SCE's Building, Renovation and Project Planning Portal. SCE's customer journey chart for new or upgraded service lays out what follows:

  • Intake. The request goes in and SCE issues a service request number, then assigns an SCE representative.
  • Documents and design. The representative asks for the project documents, reviews them, may visit the site to assess conditions, and creates and approves SCE's design.
  • Customer steps. The customer side obtains the necessary permits, submits payment for the project, signs a contract if applicable, and returns SCE's required documents before SCE builds its part.

Some city building departments, such as Costa Mesa and Laguna Niguel, require this coordination before the panel goes in. The City of Costa Mesa's residential panel upgrade standard says the SCE service planner must be contacted before work starts, for SCE's requirements and to set up the job coordination or meter spot, and that the replacement panel location must be approved by both the city and the utility. Laguna Niguel's building division handout asks for a copy of the SCE or SDG&E service order before it issues the permit. Requirements differ from city to city, so they're confirmed for your address before the work is scheduled.

One detail for the account holder: SCE's page says lockring removals or reinstalls should be requested by an authorized account holder by phone. If your job needs one, your electrician will tell you when to make that call.

Step 3: The city or county permit

The electrical permit comes from your city's building department, or from LA County Building and Safety for unincorporated areas and contract cities. Some cities publish what they want to see for a panel upgrade. Costa Mesa's standard, for example, asks for a site plan showing the existing and proposed panel locations, the Edison pole or vault, the path of the wire from SCE's connection point to the new panel, and whether the service is overhead or underground. Our permits and utilities guide lists the offices for each area we serve.

Step 4: Installation day

Expect the power to be off while the old equipment comes out and the new panel goes in. The meter belongs to SCE. Never pull the meter or open the panel's inner cover yourself; disconnecting and reconnecting the service is a coordinated step between the electrician, SCE and the inspector.

In Laguna Niguel, the city's handout says the utility generally disconnects in the morning and reconnects the same afternoon, provided the panel passes a preliminary panel inspection, and the inspection is requested the day before the utility's scheduled date. Other cities and jobs work differently, and when SCE has to change its own equipment, that work can add its own scheduling. Ask for the plan before the work is scheduled, especially if someone at home depends on medical equipment or a refrigerator full of medicine.

Step 5: Inspection and getting power back

SCE's customer journey has the customer side schedule the city or county inspection of the meter panel, and SCE receives confirmation of that inspection before it installs the meter, where needed, and energizes the service. Laguna Niguel's handout puts it simply: after inspection, the city releases the meter to the utility.

Where the time actually goes

The day of the work is usually the short part. The SCE review before it and the inspection and reconnection around it take most of the calendar.

SCE publishes targets for its own part. Its overview of the energization process sets an average of 30 business days and a maximum of 45 business days for main panel upgrade work fully under SCE's control. Those targets exclude the steps SCE doesn't control, such as the customer's documents and third-party permit processing, so they're a guide to SCE's share, not the whole project.

Things that tend to shorten the wait: keeping the panel where it is, a new service size that doesn't require SCE to change its equipment, a complete set of documents on the first submission, and a meter everyone can reach without a locked gate.

What you can do to keep it moving

  • Have a recent SCE bill handy and know who the authorized account holder is.
  • Keep gates unlocked and dogs inside on visit days: SCE's representative, the inspector and SCE's crew all need to reach the meter.
  • Plan big new loads together. Adding the EV charger, the heat pump and the ADU in one upgrade means one load calculation and one SCE review.
  • If the house has a Federal Pacific or Zinsco panel, read our note on those panels; a replacement follows the same steps.

How we can help

Infinity Electrical Inc. (CSLB C-10 #1100231) does panel upgrades for homes on SCE across Los Angeles, Orange and Ventura counties: the load calculation, the new panel and service equipment, and the SCE and building-department steps coordinated around the installation. Free estimates on eligible work; call (844) 430-7681 or use the estimate form. Customer assistance in English and Spanish.

FAQ

How long does an SCE panel upgrade take?

It depends mostly on SCE's part and on the city. SCE's published targets for main panel upgrade work fully under its control are an average of 30 business days and a maximum of 45 business days, and they don't include permit processing or the customer's documents. The installation itself is usually the shortest part.

Do I have to contact SCE myself?

Usually not for the upgrade request itself, which SCE takes through its online portal and which your electrician can coordinate. Some steps belong to the account holder, though: SCE says lockring removals or reinstalls should be requested by an authorized account holder by phone.

Does SCE charge for a panel upgrade?

Sometimes. SCE's customer journey includes a step where the customer submits payment for the project and signs a contract, if applicable, before SCE builds its part, and SCE's representative tells you what applies to your job. The permit and the electrical work are separate. SCE's project request page also describes a cost-help pilot for a limited group of electrification projects; see the eligibility list on SCE's page.

Can my new panel go in a different place?

Sometimes. Cities such as Costa Mesa require the new panel location to be approved by both the city and SCE, so a move is settled during the SCE request, before the work.

How do I know if my home is on SCE?

Check the name on your electric bill. Most of Orange and Ventura counties and most of Los Angeles County outside the City of Los Angeles are on SCE, but Burbank, Glendale, Pasadena, Azusa, Vernon, part of Cerritos and Anaheim have their own utilities, the City of Los Angeles is on LADWP, and the southern end of Orange County is on SDG&E.